Second floor walls are going up nicely. Crew is ahead of schedule. Trusses arrive Thursday. The view from the second floor is going to be incredible — you can see the harbor.
Second floor walls are going up nicely. Crew is ahead of schedule. Trusses arrive Thursday. The view from the second floor is going to be incredible — you can see the harbor.
First floor framing is complete. All load-bearing walls are in place and the inspector signed off on the floor system. Everything is looking great and we're right on schedule.
Phase reached: Framing
January 30, 2026
Foundation walls are poured and curing. Backfill is scheduled for next week. We applied the waterproofing membrane on the exterior — this will keep you dry for decades.
Excavation is complete. Footings are dug and forms are set. Ready for concrete pour tomorrow morning. Weather is looking cooperative.
Kitchen Countertop
Kitchen
Cambria Brittanicca Warm
Exterior Siding
Exterior
James Hardie Board — "Arctic White"
Master Bath Tile
Bathroom
Marble hexagon mosaic — Carrara
Front Door
Exterior
Therma-Tru Classic Craft — Mahogany
Hardwood Flooring
Interior
White Oak 5" wide plank — natural
Building Permit #2026-0142
Permit · January 8, 2026
Foundation Inspection Report
Inspection · January 29, 2026
Floor Plan — Final Rev
Plans · December 15, 2025
Elevation Drawings
Plans · December 15, 2025
Add gas line to deck for future grill
January 22, 2026
+$1,850
ApprovedUpgrade master shower to frameless glass
February 1, 2026
+$2,400
ApprovedTouch up paint — garage trim
Low priority
Kitchen cabinet door alignment (pantry)
Medium priority
Deck railing gap at north corner
Medium priority